top of page
March 2021
Ground Breaking Ceremony & Puja
April 2021
Site Progress Images
July 2021
Retaining Wall
August 2021
Aug 2021
Steel Work
Aug 2021
Steel work for Retaining wall
Aug 2021
Site Office
Aug 2021
Steel Work
1/5
Site Progress Images
September 2021
Sep 2021
Material unload
Sep 2021
Steel work for Retaining Wall
Sep 2021
Compound Wall with Retaining concrete footing
Sep 2021
Material unload
1/4
Site Progress Images
October 2021
First level Retaining Wall
Retainign Wall 2nd Level
November 2021
Retainig Wall
December 2021
RMC filling the warehouse Footing Bed
January 2022
RMC for Columns
RMC filling the warehouse Footing Bed
Internal Warehouse Footings
Jan 22
April 2022 Status
Steel offload to site and Erection
June 2022 Status
Dec 2022 Status
Final Closures
January 2023 Status
Jan 23